MBA4U.in - CAT DILR Practice Set 01
20 Original CAT-Level Data Interpretation & Logical Reasoning Questions
Static practice set | 4 sets × 5 questions | 10 MCQ + 10 TITA
| Questions | 20 |
|---|---|
| Suggested time | 40 minutes |
| Marking for practice | MCQ: +3/-1; TITA: +3/0 |
| Difficulty mix | Easy, Moderate and Difficult |
Instructions
Read the data/conditions for each set carefully. Questions within a set share the same information.
For MCQ questions, choose one option. For TITA questions, enter only the required numerical value.
Use the set as timed CAT practice. Detailed solutions appear only after all 20 questions.
All questions and datasets in this practice set are freshly written for MBA4U.in and are not reproductions of CAT questions.
SET 1: Fulfilment Centres - Order Processing - Overall difficulty: Easy to Moderate
Five fulfilment centres A, B, C, D and E processed online orders during the same week. The table gives the total number of orders, the percentage processed for same-day dispatch, and, among the orders not processed for same-day dispatch, the percentage that were delayed beyond the promised delivery window. Assume all percentages apply exactly.
| Centre | Total orders | Same-day dispatch (%) | Delayed among non-same-day (%) |
|---|---|---|---|
| A | 1000 | 40 | 10 |
| B | 1200 | 35 | 20 |
| C | 900 | 50 | 20 |
| D | 1500 | 30 | 10 |
| E | 800 | 45 | 25 |
An order is called on-time if it was either dispatched the same day or, despite not being dispatched the same day, was not delayed beyond the promised window.
Q1. [TITA] [Easy]
What is the total number of delayed orders across all five centres?
Q2. [MCQ] [Moderate]
Which centre has the highest percentage of on-time orders?
A. Centre A
B. Centre B
C. Centre C
D. Centre D
Q3. [TITA] [Moderate]
By how many does the total number of same-day-dispatch orders exceed the total number of delayed orders?
Q4. [MCQ] [Moderate]
If Centre E reduces its delay percentage among non-same-day orders from 25% to 10%,
while all other figures remain unchanged, how many additional orders become on-time?
A. 44
B. 55
C. 66
D. 72
Q5. [TITA] [Moderate]
The numbers of delayed orders at Centres B and D are in the ratio a:b in lowest terms.
What is a + b?
SET 2: Six Workshops - Scheduling - Overall difficulty: Moderate to Difficult
Six workshops A, B, C, D, E and F are scheduled in six consecutive slots numbered 1 to 6, one workshop per slot. The following conditions apply:
- A is scheduled before D.
- B and E are not scheduled in consecutive slots.
- C is scheduled either in slot 2 or in slot 5.
- F is scheduled after B.
- A and C are not scheduled in consecutive slots.
- D is scheduled exactly two slots after E.
Q6. [TITA] [Difficult]
Determine the number of feasible full timetables.
Q7. [MCQ] [Moderate]
Which of the following must be true in every valid schedule?
A. B is before C
B. A is before B
C. F is before E
D. C is before E
Q8. [TITA] [Moderate]
If C is scheduled in slot 5, how many complete schedules are possible?
Q9. [TITA] [Difficult]
If E is scheduled in slot 4, how many complete schedules are possible?
Q10. [MCQ] [Moderate]
Which of the following workshops can be scheduled in slot 1?
A. C
B. D
C. F
D. A
SET 3: Solar Plants - Net Generation - Overall difficulty: Moderate
Five solar plants P, Q, R, S and T report their annual gross generation, the percentage of gross generation consumed internally by plant equipment, and an additional outage loss.
Net generation = Gross generation × (1 - internal-consumption %) - outage loss
| Plant | Gross generation (GWh) | Internal consumption (%) | Outage loss (GWh) |
|---|---|---|---|
| P | 500 | 4 | 20 |
| Q | 600 | 5 | 30 |
| R | 450 | 2 | 21 |
| S | 700 | 10 | 35 |
| T | 550 | 6 | 22 |
Q11. [MCQ] [Easy]
Which plant has the highest net generation?
A. P
B. Q
C. R
D. S
Q12. [TITA] [Moderate]
What is the combined net generation, in GWh, of all five plants?
Q13. [TITA] [Moderate]
If Plant P increases its gross generation by 10% while its internal-consumption
percentage and outage loss remain unchanged, by how many GWh does its net generation increase?
Q14. [MCQ] [Moderate]
Which plant converts the greatest percentage of its gross generation into net generation?
A. P
B. R
C. S
D. T
Q15. [TITA] [Moderate]
If the outage loss at Plant S doubles, with all other figures unchanged,
by how many GWh would its resulting net generation exceed that of Plant Q?
SET 4: Service Hubs - Route Network - Overall difficulty: Moderate to Difficult
A service company operates six hubs A, B, C, D, E and F. Travel is possible in both directions on each direct link shown below. The number beside each link is the travel time in hours. A route may not visit the same hub more than once.
| Direct link | Travel time |
|---|---|
| A-B | 4 |
| A-C | 6 |
| B-C | 2 |
| B-D | 5 |
| B-E | 7 |
| C-D | 3 |
| C-E | 4 |
| D-E | 2 |
| D-F | 6 |
| E-F | 3 |
Q16. [TITA] [Moderate]
What is the minimum travel time from A to F?
Q17. [MCQ] [Difficult]
How many distinct A-to-F routes use at most four direct links?
A. 8
B. 10
C. 12
D. 14
Q18. [MCQ] [Moderate]
If hub C is unavailable, what is the minimum travel time from A to F?
A. 13
B. 14
C. 15
D. 16
Q19. [MCQ] [Difficult]
Which pair of intermediate hubs occurs on every minimum-time route from A to F?
A. B and C
B. C and D
C. C and E
D. D and E
Q20. [MCQ] [Difficult]
If a route from A to F must visit both D and E, in either order,
what is the minimum possible travel time?
A. 13
B. 14
C. 15
D. 16
Answer Key
| Q | Ans | Q | Ans | Q | Ans | Q | Ans |
|---|---|---|---|---|---|---|---|
| 1 | 521 | 2 | A | 3 | 1559 | 4 | C |
| 5 | 87 | 6 | 6 | 7 | A | 8 | 4 |
| 9 | 4 | 10 | D | 11 | D | 12 | 2510 |
| 13 | 48 | 14 | B | 15 | 20 | 16 | 13 |
| 17 | C | 18 | B | 19 | C | 20 | B |
Detailed Solutions
Q1. Delayed orders: A = 1000 × 60% × 10% = 60; B = 1200 × 65% × 20% = 156; C = 900 × 50% × 20% = 90; D = 1500 × 70% × 10% = 105; E = 800 × 55% × 25% = 110. Total = 521.
Q2. On-time percentage = 100% - delayed orders as a percentage of total orders. A: 94%; B: 87%; C: 90%; D: 93%; E: 86.25%. The highest is Centre A. Answer: A.
Q3. Same-day orders = 400 + 420 + 450 + 450 + 360 = 2080. Delayed orders = 521. Required difference = 2080 - 521 = 1559.
Q4.At E, non-same-day orders = 800 × 55% = 440. Reducing the delay rate from 25% to 10% saves 15% of 440 = 66 orders. Answer: C.
Q5. Delayed orders at B and D are 156 and 105. Their ratio is 156:105 = 52:35. Hence a + b = 87.
Q6. The six valid schedules are: ABFECD, BAFECD, BCEADF, BCFEAD, BFAECD and EADBCF. Hence there are 6 valid schedules.
Q7. Checking all six valid schedules shows B always occurs before C. The other statements fail in at least one schedule. Answer: A.
Q8. Four valid schedules have C in slot 5: ABFECD, BAFECD, BFAECD and EADBCF. Therefore the answer is 4.
Q9. The schedules with E in slot 4 are: ABFECD, BAFECD, BCFEAD and BFAECD. Therefore 4 schedules are possible.
Q10. The first workshop can be A, B or E across the valid schedules. Among C, D, F and A, only A can occupy slot 1. Answer: D.
Q11.
Net generation:
P = 500 × 0.96 - 20 = 460
Q = 600 × 0.95 - 30 = 540
R = 450 × 0.98 - 21 = 420
S = 700 × 0.90 - 35 = 595
T = 550 × 0.94 - 22 = 495
The maximum is Plant S.
Answer: D.
Q12. Combined net generation = 460 + 540 + 420 + 595 + 495 = 2510 GWh.
Q13.
New gross generation at P = 550 GWh.
New net = 550 × 0.96 - 20 = 508 GWh.
Original net = 460 GWh.
Increase =
48 GWh.
Q14.
Net as a percentage of gross:
P = 92%
Q = 90%
R = 420/450 = 93.33%
S = 85%
T = 90%
The largest is Plant R.
Answer: B.
Q15.
If S outage loss doubles to 70 GWh:
New net = 700 × 0.90 - 70 = 560 GWh.
Plant Q remains at 540 GWh.
Difference =
20 GWh.
Q16.
A-C-E-F takes:
6 + 4 + 3 = 13 hours.
Another minimum route is A-B-C-E-F:
4 + 2 + 4 + 3 = 13 hours.
Therefore the minimum travel time is
13 hours.
Q17.
The 12 simple A-F routes using at most four links are:
A-B-C-D-F
A-B-C-E-F
A-B-D-E-F
A-B-D-F
A-B-E-D-F
A-B-E-F
A-C-B-D-F
A-C-B-E-F
A-C-D-E-F
A-C-D-F
A-C-E-D-F
A-C-E-F
Therefore there are
12 routes.
Answer: C.
Q18.
With C unavailable, the best route is:
A-B-E-F = 4 + 7 + 3 = 14 hours.
Therefore the minimum travel time is
14 hours.
Answer: B.
Q19.
The minimum-time routes are:
A-C-E-F
A-B-C-E-F
The intermediate hubs common to both are
C and E.
Answer: C.
Q20.
A route visiting both D and E can achieve 14 hours:
A-C-D-E-F = 6 + 3 + 2 + 3 = 14.
No 13-hour route contains both D and E.
Answer: B.
MBA4U.in | CAT DILR Practice Set 01 | Original Practice Material